On Wed, Oct 4, 2023 at 7:19 PM Kushagr Gupta <kushagrguptasps.mun@gmail.com> wrote:
Hi Milind,
Thank you for your swift response.
How many hours did you wait after the "start time" and decide to restart mgr ? We waited for ~3 days before restarting the mgr-service.
The only thing I can think of is a stale mgr that wasn't restarted after an upgrade. Was an upgrade performed lately ? Did the dir exist at the time the snapshot was scheduled to take place. If it didn't then the schedule gets disabled until explicitly enabled.
There was one more instance where we waited for 2 hours and then re-started and in the third hour the schedule started working.
Could you please guide us if we are doing anything wrong. Kindly let us know if any logs are required.
Thanks and Regards, Kushagra Gupta
On Wed, Oct 4, 2023 at 5:39 PM Milind Changire <mchangir@redhat.com> wrote:
On Wed, Oct 4, 2023 at 3:40 PM Kushagr Gupta <kushagrguptasps.mun@gmail.com> wrote:
Hi Team,Milind
Ceph-version: Quincy, Reef OS: Almalinux 8
Issue: snap_schedule works after 1 hour of schedule
Description:
We are currently working in a 3-node ceph cluster. We are currently exploring the scheduled snapshot capability of the ceph-mgr module. To enable/configure scheduled snapshots, we followed the following link:
https://docs.ceph.com/en/quincy/cephfs/snap-schedule/
We were able to create snap schedules for the subvolumes as suggested. But we have observed a two very strange behaviour: 1. The snap_schedules only work when we restart the ceph-mgr service on the mgr node: We then restarted the mgr-service on the active mgr node, and after 1 hour it started getting created. I am attaching the log file for the same after restart. Thre behaviour looks abnormal.
A mgr restart is not required for the schedule to get triggered. How many hours did you wait after the "start time" and decide to restart mgr ?
So, for eg consider the below output: ``` [root@storagenode-1 ~]# ceph fs snap-schedule status /volumes/subvolgrp/test3 {"fs": "cephfs", "subvol": null, "path": "/volumes/subvolgrp/test3", "rel_path": "/volumes/subvolgrp/test3", "schedule": "1h", "retention": {}, "start": "2023-10-04T07:20:00", "created": "2023-10-04T07:18:41", "first": "2023-10-04T08:20:00", "last": "2023-10-04T09:20:00", "last_pruned": null, "created_count": 2, "pruned_count": 0, "active": true} [root@storagenode-1 ~]# ``` As we can see in the above o/p, we created the schedule at 2023-10-04T07:18:41. The schedule was suppose to start at 2023-10-04T07:20:00 but it started at 2023-10-04T08:20:00
seems normal behavior to me the schedule starts countdown for 1h from 2023-10-04T07:20:00 and created first snapshot at 2023-10-04T08:20:00
Any input w.r.t the same will be of great help.
Thanks and Regards Kushagra Gupta