Next point release
We plan to test and release octopus 15.2.12 in the next 2 weeks. Please label PRs appropriately (add "<release>-batch1" and "needs-qa" labels) so they can be tested and included in that release on time. The repo will be locked for merging in ~1 week (planned for 5/22/21). Thx YuriW
Just a reminder, if you have any PRs targeting next octopus next point release, it's a good time to raise them now. On Wed, May 12, 2021 at 7:49 AM Yuri Weinstein <yweinste@redhat.com> wrote:
We plan to test and release octopus 15.2.12 in the next 2 weeks. Please label PRs appropriately (add "<release>-batch1" and "needs-qa" labels) so they can be tested and included in that release on time.
The repo will be locked for merging in ~1 week (planned for 5/22/21).
Thx YuriW
participants (1)
-
Yuri Weinstein